Slateford Green – 2007/08 Landscaping Upgrading

The residents association received the following breakdown on what will be happening over the next year to improve our general landscape:

The format is in following order:
  • Action
  • Completed by date
Here is the list:
  • Remove chespale fencing at entrance barrier.
  • End of April ‘07
  • Replant railway fenced area with laurel and dogwood shrubs to provide additional cover
  • Oct / Nov ‘07
  • Prepare and apply fertilizer to grasscrete areas throughout Slateford Green.
  • May
  • Maintain and replant Community Centre planted areas.
  • May
  • Beech hedging - Remedy by infilling where appropriate with Escallonia and transplanting beech hedging to provide uniformity of appearance
  • Spring planting followed by autumn replanting
  • Remove chespale fencing from front gardens at 4,5,6 & 7.
  • May ‘07
  • Grasscrete opposite stairs 8 – 9 apply top soil and reseed.
  • May
  • Wooded area adjacent to allotments. Apply top soil, grass seed .
  • May
  • Banked are adjacent to pump chamber – remove upper chespale fencing – plant area with dogwood & laurel
  • May
  • Stairs 13 -16 remove chespale fencing on road side
  • June
  • Develop plan or improvement of visitors parking spaces.
  • July

Internal
  • Ensure hedging is trimmed to fence height throughout internal garden area
  • May
  • Island bed – remove jaggy shrubs and replace with specimen tree
  • July